Wye River Road Upgrade Works

  • Project typeRoad Infrastructure Upgrades
  • Contractor nameMarchese Excavations & Bin Hire
  • Completion Date23 October 2026
Wye River Entrance Sign.jpg

The completion of the Koonya Avenue and The Boulevarde road upgrade works has been extended, with works now expected to be completed in late November 2026.

The revised completion date is due to a combination of factors, including:

  • Wet weather earlier in the project, resulting in approximately two weeks of lost construction time.
  • Delays in the delivery of kerb and channel components required for the works.
  • Unforeseen pavement conditions encountered during reconstruction works on The Boulevarde, where soft areas beneath the existing road pavement were identified. Additional excavation and pavement rehabilitation works have been required to ensure a durable and long-lasting road outcome.
  • The decision to undertake works on The Boulevarde one lane at a time to maintain traffic access during construction. This approach was adopted following community feedback and, while minimising disruption to residents and road users, has extended the overall construction program.

To support safe and efficient construction, traffic management will be in place. This will include road closures and detours at different times throughout the project. 

The Boulevarde Carpark will be closed throughout the construction period and used for the storage of construction materials and machinery.

There will be local resident access only through the construction site. Waste collection services will continue as usual.

These measures are in place to keep the public and construction crews safe and to help the works progress as quickly as possible.

Planned work includes:

  • minor drainage upgrades
  • minor kerb and channel upgrades
  • road reconstruction work
  • retaining wall construction.

Please check the project maps for details on detours, closure dates and access changes.

Please note that construction schedules may change due to weather, site conditions, or other unforeseen circumstances.

Scheduled Work - Stage One

Stage One: 17 August to 5 September (subjected to favourable weather conditions)

Wye River Roadwork Stage 1.jpeg

 

 

Scheduled Work - Stage Two

Stage Two: 7 September to 26 September (subjected to favourable weather conditions)

Wye River Roadwork Stage 2.jpg

 

Scheduled Work - Stage Three

Stage Three: 28 September to 21 October (subjected to favourable weather conditions)

Wye River Roadwork Stage 3.jpg