The completion of the Koonya Avenue and The Boulevarde road upgrade works has been extended, with works now expected to be completed in late November 2026.
The revised completion date is due to a combination of factors, including:
To support safe and efficient construction, traffic management will be in place. This will include road closures and detours at different times throughout the project.
The Boulevarde Carpark will be closed throughout the construction period and used for the storage of construction materials and machinery.
There will be local resident access only through the construction site. Waste collection services will continue as usual.
These measures are in place to keep the public and construction crews safe and to help the works progress as quickly as possible.
Planned work includes:
Please check the project maps for details on detours, closure dates and access changes.
Please note that construction schedules may change due to weather, site conditions, or other unforeseen circumstances.
Stage One: 17 August to 5 September (subjected to favourable weather conditions)
Stage Two: 7 September to 26 September (subjected to favourable weather conditions)
Stage Three: 28 September to 21 October (subjected to favourable weather conditions)
Koonya Avenue and The Boulevarde, Wye River 3234 View Map
Koonya Avenue and The Boulevarde , Wye River 3234